Thomas Merton- June 12/20 construction update

We now have 88 days remaining! Delivery and placement of RTU’s is a major milestone! Once this task is complete allows the completion of ceilings / hallway.

Classrooms- metal duct is now connected to heat pumps. Next week we will be framing bulkhead around heat pumps. Once complete/ all classrooms can be boarded, mud and painted. This would allow framing of T-bar ceilings.👍 – we need flooring contractor on board to make good floor tiles /classrooms

Hallways- prior to delivery of roof top units??? / all curbs to be watertight and supported from below. Once Rtu’s are in place allows ceilings to be framed / hallway.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: