Bishop Reding CSS- June 22/20 construction update

0 Comments

Childcare – as per critical path we cannot move forward until plywood/parapet is installed. Once complete would allow our roofers to watertight our building. Urgent
Cafeteria- waiting for completion of plywood parapet.
SOG re- Cafeteria soon to be poured.
Addition- masonry contractor finishing up brick veneer.
Science rooms- demolition continues
Steel Stud /admin office / now in place

As noted/ Addition/ July 8th is when we begin fire verification then we push for occupancy. Lockers, Millwork, Classroom doors and hardware come into play. July will be a busy month.

Starting to shape roadway