Curbs – 4 curbs are now watertight.One curb remaining to be watertight.
Looking from underneath re- curbsDrywall contractor is framing bulk-heads re- windows and heat pumps. We are concentrating completion of classrooms. Flooring contractor is also needed to make good all tile.
Prior to installing T-bar ceilings drywall requires mud, sanding and paint . While I am on a roll “ What is the plan for painting???” This could be interesting.
Work in mechanical rooms continues.Note as per schedule above. All drywall and T-bar complete prior to July 20th /gulp/ ‘To zoom-in hover over schedule with your mouse and if mobile use your finger” believe it or not I have to explain this to people hahaha!