Thomas Merton -June 22/20 renovation update

0 Comments

Curbs – 4 curbs are now watertight.
One curb remaining to be watertight.
Drywall contractor is framing bulk-heads re- windows and heat pumps. We are concentrating completion of classrooms. Flooring contractor is also needed to make good all tile.
Note as per schedule above. All drywall and T-bar complete prior to July 20th /gulp/
‘To zoom-in hover over schedule with your mouse and if mobile use your finger” believe it or not I have to explain this to people hahaha!