Bishop Reding July 2/20 construction update

Cafeteria / Front Entrance

Admin office is being taped and painted
Science Rooms
Roof inspection- cafeteria / childcare
Addition- all T-bar to be in place prior to July 8th
Addition- T-bar needed stairwell
Addition – classroom doors are being hung
Addition- waiting for Millwork