*

merry christmas

Merry Christmas

Bishop Reding July 2/20 construction update

Cafeteria / Front Entrance

Admin office is being taped and painted
Science Rooms
Roof inspection- cafeteria / childcare
Addition- all T-bar to be in place prior to July 8th
Addition- T-bar needed stairwell
Addition – classroom doors are being hung
Addition- waiting for Millwork

Author: Larry Arbuckle

Working a lifetime in construction has taught me communication is everything. Flying drones gives me the edge on seeing construction progress from above. Every picture tells a story and a video tells a thousand stories.

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: