Thomas Merton July 6/20 – Reno update

I recommend a date be set re- fire verification. Once confirmed would allow trades to zero in and complete their task. Occupancy would follow. We have 64 days remaining before school begins.

Flooring contractor starting placement of floor tile.
Time to think about removing garbage.
as per schedule T-bar to be complete prior to July 31st.