merry christmas

Merry Christmas

Bishop Reding CSS- July 8/20 construction progress

Good news! AVB is being applied / Childcare/ brick veneer to follow
Addition /Science Rooms- placement of sheet vinyl is ongoing. We need to complete science rooms ASAP allowing placement of Millwork.
Contractor / SOG/ returns tomorrow.
Science Rooms existing school- grinding / removal of glue / continues .
New Admin Office.- ongoing
Roof inspection / childcare – cafeteria. It appears our childcare is ready for George Roque.