Bishop Reding CSS- Aug 10/20- 3 weeks remaining.

Admin Office. Contractor installing flooring. Complete by Wednesday.
Aerloc- where are we with glass /front entrance And cafeteria ????
Addition- contractor spraying beams re- fire spray.
Eye wash stations are installed / addition science rooms. We also require glass and hardware installed in classroom doors re- occupancy.
Addition- lockers are being placed.
Guidance room requires completion of ceiling and floor.
Former Science Rms. Wall brackets are being installed.