Electricians are placing all wire above T-bar. I am told tomorrow drywall contractor will be placing tile / hallways/ estimated time for completion 4 days. Starting next to CPP room and proceeding down all hallways.I am told flooring contractor arrives Monday and make good hallwaysCPP room – handrails and door frame neededCPP – Servery- floor has been prepped for vinyl – millwork is being installed- painters are painting wallsCPP Room- partition being installed washroomCPP room- air handling units are being started.The Region has told me / main waterline/ pressure test has passed- sample to be sent to Lab Monday – results by Wednesday .Masonry contractor working Library / CafeteriaOne beam is in place / front entrance/ 2 longer beams arrive Monday. Once in place beams require fire spray.
I will be returning tomorrow for a further update.