Nelson High School – Aug 21/20- update

Electricians are placing all wire above T-bar. I am told tomorrow drywall contractor will be placing tile / hallways/ estimated time for completion 4 days. Starting next to CPP room and proceeding down all hallways.
I am told flooring contractor arrives Monday and make good hallways
CPP room – handrails and door frame needed
CPP – Servery- floor has been prepped for vinyl – millwork is being installed- painters are painting walls
CPP Room- partition being installed washroom
CPP room- air handling units are being started.
The Region has told me / main waterline/ pressure test has passed- sample to be sent to Lab Monday – results by Wednesday .
Masonry contractor working Library / Cafeteria
One beam is in place / front entrance/ 2 longer beams arrive Monday. Once in place beams require fire spray.

I will be returning tomorrow for a further update.