Cafeteria / Front Entrance – waiting for windows and curtain wall. Aerloc please expedite allowing us to complete the inside.

Drag mouse along floor plan and click

Childcare
Pre-schooler Washroom Toddler Hallway Infants

Pre-schooler

Pre- Schooler classroom

Washroom

Washroom

Toddler

Hallway

Infants


Demolition of our existing kitchen

Existing Cafeteria
Childcare- We are pushing for completion prior to Oct 1st- Task to be completed:
Aerloc- front doors needed
interior- vinyl floor needed
front entrance doors needed and all interior doors
all Millwork to be installed
permanent power required