St. Peter childcare- Sept 21/20- const update.

Footings are an estimated 60% complete. Foundation Walls are scheduled to begin mid/end of this week. Going forward plumbing undergrounds can start next week. SOG to follow. We are pushing to be closed in / including windows and roof / prior to Dec 1st. We require onsite – all HM DR frames/ bearing plates/ and galvanized lintels re- windows. We will be eating our Christmas turkey in a watertight building.