Nelson High School – Sept 25/20- construction update

We are now forming remaining curb and sidewalk /Cosmetology. Once poured Would allow our Landscaper /Oakridge/ to complete their scope of work. Also noted: lighting poles parking area can now be installed.
New Cafeteria / I am told on Monday we will be preparing the floor / slab on grade/ and are scheduled to pour The following Monday. Starting Monday the Library floor / 2nd floor above/ will also start preparing / pouring of concrete floor. We are pushing both floors to be poured complete- Mid October
New Kitchen Classroom. – Exhaust Hoods are now onsite and waiting to be hung.