Bishop Reding CSS- construction update – Oct 20/20

Cafeteria – Painters are now onsite!
Former Kitchen – Demolition continues – removing duct / kithen exhaust.

Our new addition /childcare / is fully operational. Demolition of the former childcare has now started / once complete we start building our new gym.

Going forward :

complete demolition of former kitchen

work continues / existing cafeteria / main entrance/ new cafeteria and cooking classroom.