New Cafeteria – Masonry contractor continues building walls.

Video shows where we were last year on Nov 28th

New Cooking Classroom- Metal Duct is now being installed

Cosmetology – we are now watertight – roof drains are now connected. Thought: temporary heat needed soon.

Manufacturing Room nearing completion.