Nelson High School – Nov 9/20 – update

Slides above show plywood being installed / parapet/ and masonry contractor building walls re- new entrance. I am told roofing contractor arrives – end of this week πŸ‘πŸ‘πŸ‘πŸ‘πŸ‘

Thought: library floor to be poured ASAP. After pour Contractors would be able to load their material prior to installation of windows.

New Cafeteria – installation of sprinkler continues