Bishop Reding – Nov 11/20 – construction update

Starting our footings – New Gym
Main entrance – painting continues / electrician installing light fixtures
Preparing floor re- new fridge / freezer – kitchen.
New Cafeteria- work continues / metal duct.

We are heading in the right direction as every day shows progress. We are pushing completion of the main entrance and new cafeteria / first of next year/ Jan – Feb. Footings are proceeding well / new gym/ once complete allows our masonry contractor to build above ground. Everyone will notice progress / masonry/ once they start.