St. Peter- childcare- Nov 11/20 progress

Masonry walls near completion.
All masonry walls scheduled for completion – end of this week.

We are disappointed Open Web Steel Joist has been delayed. Our steel contractor was notified back on Oct 2nd steel would be needed soon. Please expedite this task as we will be at a standstill Monday morning.