Nelson High School – Nov 27/20 update

Base [2] /parking area lighting/ have now been poured.
Cosmetology – siding has naw been installed
Cosmetology – floor tile has now arrived . Contractor to follow.
CPP rm- exterior siding is being installed
MTI rm- near completion – floor is being painted.
Cooking classroom- Installation of concrete wall board near completion
Library- I am told roofing contractor arrives Tuesday . Thought : start thinking of Temporary Heat. Once we are watertight allows the arrival of finishing trades.