Nelson High School- Dec 1/20 update


Library / Cafeteria – roofer has arrived and has loaded material on the roof. Thought now is / temporary heat will be needed allowing finishing trades to complete their tasks. Click on link for 360 and drag your mouse

http://360.io/J9frF6

Siding now complete CPP rm
Interest now is starting the 2 washrooms as per above drawing. I understand they need to be emptied of material and storage.🔨🔨😜