Bishop Reding Dec 7/20 – Reno update

Cafeteria/Front Entrance – Aerloc is onsite trimming out windows and exterior doors. Looking good.

New Cafeteria- ceiling appears to have been painted / sprayed. Floor finishes next!

New Kitchen/ new floor finish👍

Kitchen Washroom – toilet partitions are being installed.

Entrance to school to be made good.

Theatre- existing floor tiles are being removed.

New Gym / Weight Room- Electricians are removing conduit from wall / existing gym. Foundation walls are being back-filled complete with compaction. The cold kept masonry contractor from working But weather appears favourable tomorrow. We need steel “OWSJ” and lintels.

We are going the right way👍