Bishop Reding CSS – Jan 8/21 – Const update

Sadly, we lost our captain over the holidays and prayers and thoughts are with his family. Brad Harrington / our Site Superintendent / came to work every day to lead our troops. I am keeping Brad on my email distribution list allowing him to review our progress updates from above. RIP buddy and SYOTOS.

Front Entrance- the guys are placing floor tile in the cafeteria. I understand the kitchen equipment is arriving this week. The end is near.👍
New Gym- Mud has been removed and replaced with stone. The guys are laying out the weepers.. Next week Masonry contractor returns to complete walls..