St. Peter- childcare- Const progress- Feb 17/21

Ceramic tile being placed / hallways

Wall tile & Floor tile being placed /washrooms.

Classroom ceilings are now framed /T-bar/ Electricians are installing lights. We are now ready re- flooring in the classrooms followed by Millwork. We are pushing for completion / end of March. Date for fire verification needed.

Domestic hot water tank is now installed complete with plumbing.

Janitor sink now installed.