Bishop Reding- March 15/21- update

New Gym- once work re- ceiling is complete / painters to arrive.

New Weight Room- work continues above ceiling. Once complete would allow the arrival of painters.

Theatre- seating near completion.

Former staff rooms- demolition continues.

New classrooms 2nd floor. Seams /flooring/ are being welded- base needed.

Dance Rms- doors needed / entrance.

DCIM\110MEDIA\DJI_0337.JPG

Spraying of AVB continues.