St. Peter – childcare- March 23/21 update

Sheet goods- vinyl is now being installed ๐Ÿ‘

Toilet fixtures are being installed – waiting for partitions.

We are closing in / on completion of this project.

Tasks to be completed:

Counter tops needed Millwork / toilet partitions needed / concrete pads poured – exits /completion ceramic and vinyl flooring- fire verification- all exterior work. The end is near๐Ÿ˜ƒ