Nelson High School – Reno update- April 6/21

Auto-body / floor has been poured.

Kitchen – connection of equipment ongoing.

New cafeteria- we are pushing to install entrance doors complete with glass . Our goal is to remove plywood hoarding ASAP.. Also note : we require overhead lights powered ASAP. Wiring [green circle] has been pulled to panel re- overhead lights. πŸ”¦πŸ”¦

New Library. Painters are onsite – walls and ceiling. Once complete allows arrival of flooring contractor.

We are pushing for completion : new library, cafeteria and new kitchen mid May.🐎🐎🐎