Bishop Reding CSS – April 12/21- Const update

Above- Front of school/ remedial work needed prior to pouring of concrete walkway.

Above- Painters working in existing Gym. Light fixtures needed new Gym. Right.

Dance Room – Lift is being installed.

T-bar ceiling has now been framed in hallway and new weight room.

default

Grading appears to be complete / exterior new gym.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.