Bishop Reding – Const progress – April 14/21

New Gym- exterior work continues / grading of sub grade and forming for concrete slab/ door exit. Excess dirt / soil -scheduled for removal tomorrow.

Gym – floor to be ripped up and replaced with new.

Painting of existing gym / near completion.

Rooms on main floor – in need of new flooring.

Lift / dance room/ scheduled for completion tomorrow.