Bishop Reding – Const update- May 10/21

Contractor building concrete curbs and sidewalk- New Gym

Front of school- asphalt top coat required.

Gym – flooring is being removed.

Room adjacent to Gym- shelving is being installed

Painters are onsite.

Rooms / main floor/ near completion.

We are pushing completion – end of this month👍