Nelson High School- May 18 /21 Tasks to be completed.

Cafeteria- doors are being hung / drywall taping ongoing

Library- starting placement re- carpet tile

New Elevator- water proofing re- foundation wall required.. Curtain wall to be removed to allow building of elevator shaft.

Cosmetology-additional landscape needed and metal panel installed above entrance required.

Parking area posts [3] are needed. Posts are onsite.