Milton #10 CES- Const update- footings have now started.

default
default

Today, we have started our footings. Progress is needed allowing the start of our masonry contractor ASAP. Note- hollow metal frames /doors/ are needed onsite prior to masonry contractor building above ground. M&E contractors are to follow with undergrounds. Video below is where we need to be 1st week of July.