Milton #10 CES- const progress – May 28/21

Left May 26 / 21 Right May 28/21

Footings are progressing well. Full Kudos to the boys today as it was pouring rain and they were still excavating their footings.

Note: perhaps we should start thinking about placement of stone[parking], pouring concrete curbs and sidewalks plus base asphalt/ where applicable. As you can see the site appears muddy and the mud will kill us.