Courtyard- the guys are forming / concrete pathway

Body-shop- floor has been painted prior to delivery of equipment .
Elevator. Hoarding main floor Hoarding 2nd floor
Elevator – we are good to go.
Ongoing work – washroom and storage rms.

Photography Rooms- work ongoing

We are pushing for completion prior to Labour Day! Below is our theme song on this job!