We are pushing for completion prior to return of school /Sept. Below are tasks to be complete.
Body Shop – waiting for equipment- walls to be painted Many openings /7/ require door frames/doors and masonry work-paint Terrazzo repair needed – hallway Rebuilding of washroom required Photography rooms require remedial work New Library- counter top required. Finish needed beneath bridge. Health room to be complete Courtyard- to be landscaped.
Above – masonry shaft needed – elevator.

Behind School- Make Good???