Above/ Body Shop- Spray Booth is now onsite / wall framed with metal stud. Installation of booth starts next week.

Existing washroom /change room/ preparation for demolition.

New elevator- scaffold can now be erected allowing elevator shaft to be built. Masonry contractor to arrive early next week to complete their work. Once complete allows other trades to complete their tasks. Pushing for completion prior to September.