Nelson High School – July 13/21 – construction update

Masonry contractor is now onsite building walls / starting in Tech rms. Masonry contractor to stay onsite and complete their tasks as per contract. Once complete allows finishing trades to complete their work /painters-flooring-Millwork etc. We are pushing for completion prior to Sept.

Washroom has been cleaned and ready to be re-built.

Body shop- still waiting arrival of installers / building of spray booth.

Installation of manhole near completion- Once complete / scheduled for tomorrow / would allow masonry contractor starting elevator shaft.

Again, we are pushing for completion prior to September.