Milton 10 CES – Const update – July 15/21

Aerial View.

Slab on Grade appears to be 40% complete.

M&E contractors to place in ground piping ASAP. We are pushing pouring all SOG prior to Aug 1st.

Plenty of action happening inside the school- now let’s turn our attention on the exterior. Status of electrical transformer and vault. We need primary and secondary lines in place ASAP. Also looking at rear parking adjacent to childcare. It is a good time to start our parking area. πŸ‘πŸ‘πŸ‘πŸ”¨πŸͺš

Again, below is where we need to be Aug 31st