Nelson High School – July 21/21 Const progress July 21, 2021July 25, 2021 Roof over auto-body classroom. Contractor cutting metal duct penetrating the roof.Auto-body classroom- contractor insulting pipe prior to boarding of drywall. Above- Masonry now complete / Tech rms/ Ready for paint. Health Rm. Framing of metal stud startedAdmin Rm- framing of metal stud started. New Elevator- waiting on the arrival of scaffold. 48 days remaining until start of school.👁 Share this:Click to email a link to a friend (Opens in new window)Click to share on WhatsApp (Opens in new window)Click to share on Twitter (Opens in new window)Click to share on Facebook (Opens in new window)MoreClick to share on Reddit (Opens in new window)Click to share on LinkedIn (Opens in new window)Like this:Like Loading... Related