Milton #10 CES- Aug 6/21- Const progress August 6, 2021 Starting / building of non load bearing masonry wallsSOG 60% completePouring SOG scheduled for this afternoon.Head Wall needed- once built would allow construction of our parking area.Steel scheduled for next week/ pre-cast the week after.Below right / childcare. Share this:Click to email a link to a friend (Opens in new window)Click to share on WhatsApp (Opens in new window)Click to share on Twitter (Opens in new window)Click to share on Facebook (Opens in new window)MoreClick to share on Reddit (Opens in new window)Click to share on LinkedIn (Opens in new window)Like this:Like Loading... Related