St. Mark CES – precast now in place

Masonry Contractor is now onsite as precast is now placed. We are pushing to start our roof end of this month / first of November. I did not see lintels /windows/ onsite. Open web joist re- roof are needed soon. Work completing retaining wall (stone) can now begin. All trades note: progress will happen quickly!

Stage is ready for sprinkler, lighting and diffusers.

Safety & handrails rails are now in place.

“Lead, Follow Or Get Out Of Way”

St. Mark CES- precast arrives Oct 1st

This project will be firing back up Oct 1st as we are scheduled for precast! Once placed, sprinkler and plumbing pipe can be hung as well as electrical conduit!
As discussed, we are pushing for a Jan 1st 2019 completion! Ensure all material is onsite!

Stage area: sprinkler line re- drops to be complete this week-end. Once complete T-bar ceiling needed  with lights

IMG_4929

Locker base (addition) to be formed and poured ASAP!

“The Push is On”

“Lead, Follow Or Get Out Of Way”