St. Nicholas CES- 32 days remaining

2nd floor- waiting for ceramic tile Contractor./ floor/. Lockers scheduled – Dec 2nd.
Waiting – all classrooms ready for sheet goods.
2nd floor ceiling adjacent to washrooms ready to be framed followed with boarding.
2 heating units have been fired up. Inside now warm and toasty.
Starting installation metal duct – Gym
I Beam has now received spray /fire. We are boarding /ceiling/ Wed.

We are coming together On the inside but /Arrowhead / we need you on the exterior. The forecast – end of this week and next Is favourable re- Concrete curbs, sidewalks and asphalt. May the force be with you. We are going in the right direction👍

Drones coming to Milton- next year

I am sharing this story from InsideHalton.com:
“‘Innovative’: Drone delivery service takes flight in Milton next year”

Please visit the following page for more information:
https://www.insidehalton.com/news-story/9678631–innovative-drone-delivery-service-takes-flight-in-milton-next-year/?s=e

** Disclaimer **

Metroland Media Group Ltd. and its affiliated sites are not responsible for the content of this e-mail. Please note that neither the e-mail address nor name of the sender has been verified.

https://larryarbuckle.com

St. Nicholas- 37 days remaining

37 days remaining- weather permitting we will be 100% watertight Friday nite. Flynn to remove their trailers ASAP. Everyone be aware this job is real “Lead, Follow or Get Out Of The Way”
Konrad! You now have the bulls eye. Flooring is now on our critical path. Max has full control- as hallways and washrooms are cleaned and free of debris.
All classrooms are ready re- flooring. We need action. All trades note: We are closing the building next week. All windows for 2nd floor will be installed. Ensure material is delivered now allowing the use of a lift/ 2nd floor
Ceilings are now being boarded. All trades ensure work above is complete as well as inspections.
Admin office is now watertight. Everstrong to place window and door frames allowing us to board and install ceilings.
We are now watertight in the Library. Anvi please ensure all roof drains are connected.
Counter tops arrive in 2 weeks
Arrowhead Paving placing stone- curbs Monday
Landscaping Contractor is on board
CEC working on Parking Lot Lighting
Gas meter arrives tomorrow
Everyone stay tuned- progress is ongoing