St. Nicholas CES- secondary duct bank now in place

The guys are working on the final touches of secondary duct ( electrical) bank👍 Now complete!

Electrical conduit stubbed into building!

75%-80% of SOG is now poured

Hovering over top of washroom / now rouged in!

Scope:

Early next week steel arrives / followed with precast!

By the first week of June we are heading for the roof!

On Deck: OWSJ

www.larryarbuckle.com
🦅🦅🦅🦅🦅

St. Nicholas CES – Electrical Duct Bank

As per discussion on site today: It was revealed/ now would be a good time to remove existing elec duct bank and replace with new- prior to precast. I am told Everstrong to remove existing elec duct and CEC build a new elec duct. Please initiate the paperwork allowing this task to be complete ASAP. Let’s take advantage of the lull before the arrival of precast [mid May]

We are still pushing / pouring SOG / scheduled for this Thursday [ weather permitting]

Below: video of construction progress to date: