BR Update June 5th

Drainland started silt fence today, will continue silt fence and then construction fence Monday

Guido expects to start actual removalsapprox Tuesday next week

Site Service Permit and Regional Permit have been distributed.

Massimo please confirm is there a trailer with permits and NOC posted or does Drainland hold these permits until Percon is mobilized?

Discussion with Guido/Chirag yesterday – to save time and $proposed to grout existing storm lineat the N driveway rather than remove. Chirag to issue instruction confirmingdetails .

S/S shop drawings returned. Drainland to ensure the U/G chambers fulfill the required capacities. Specified OGS is required as previously discussed.

Incon/DEI working on switchboard solution. Please advise

We finally received building permitcomments from the Town today. We will prepare and submit a response.

regards,

www.larryarbuckle.comπŸ¦…πŸ¦…πŸ¦…πŸ¦…πŸ¦…

St. Nicholas CES- standing room only

Site is very busy today as precast continues being placed! If you stand still on this job you will receive β€œwindburn”

Site Service contractor has dropped off piping and scheduled installation this week!

Masonry contractor now on 2nd floor! Open Web Steel Joist to arrive -end of this month- Roof start mid July. Mechanical equipment arrive the week of June 17th. Housekeeping pads to be in place.

Paving contractor to follow site service contractor with stone- prevent mud!

On Deck- windows

www.larryarbuckle.com
πŸ¦…πŸ¦…πŸ¦…πŸ¦…πŸ¦…

St. Nicholas- standing steel

Steel being erected /in preparation/ of precast arriving Monday

Front of building- masonry contractor building walls!

Precast scheduled for Monday / 2nd lift/ once placed masonry contractor to begin 2nd floor! On Deck: OWSJ end of June!