Bishop Reding – April 1/20- update

Childcare – 3/4 stone is now being placed prior to SOG. Once slab is poured allows masonry contractor to build above ground.
Cafeteria- Mirage Steel is onsite erecting steel
Addition / Courtyard- Brick veneer near completion scheduled for completion Friday nite. Landscape contractor is on board and will be onsite soon.
Addition exterior- Brick veneer is progressing well and should be wrapping up by the end of this month / weather permitting.
Addition- light fixtures are now onsite waiting for T-bar ceilings.
Addition- remaining locker base to be poured ASAP.
Work is Progressing Well

1 thought on “Bishop Reding – April 1/20- update

  1. Donald Trump says:

    Masons crashed that foundation in one day why’s it taking so long to get back fill done Larry??

    Reply

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: