Childcare – 3/4 stone is now being placed prior to SOG. Once slab is poured allows masonry contractor to build above ground.Cafeteria- Mirage Steel is onsite erecting steelAddition / Courtyard- Brick veneer near completion scheduled for completion Friday nite. Landscape contractor is on board and will be onsite soon.Addition exterior- Brick veneer is progressing well and should be wrapping up by the end of this month / weather permitting. Addition- light fixtures are now onsite waiting for T-bar ceilings.
Addition- Walls are being painted and floors are receiving a skim coat patch. We are ready for ceramic tile in the hallways. We have 75 days remaining / completion of the addition.Addition- remaining locker base to be poured ASAP.
Masons crashed that foundation in one day why’s it taking so long to get back fill done Larry??