Childcare – Weather has delayed us today resulting in our pour tomorrow/ SOG . On Wednesday we will be ready for masonry contractor.Cafeteria-We await arrival steel deck / roof / tomorrow. Weather delayed us today.Courtyard. I understand brick veneer will be complete mid week. RRG landscape was onsite and will be starting end of this week.Addition / Brick Veneer scheduled for completion end of this month.Addition- HERE’S THE PLAN: Painting contractor arrives Wednesday starting final coat in hallway / main floor. Right behind them T-bar ceiling /grid/ will be installed complete with placement of light fixtures. Right behind T-bar we start installation of ceramic tile/ hallway. We should be in full throttle end of this week.
Also note: when pouring SOG / childcare/ we will also be pouring remaining locker base in addition.