Bishop Reding CHS- May 15/20- update

Cafeteria- metal deck /roof/ now in place.
Exterior- brick veneer ongoing.
Cafeteria- SOG now poured complete with saw cuts.
Painters are now onsite painting classrooms main floor.
Locker base have all been poured.
Stairwell- ceiling being framed.