Bishop Reding CHS- May 6 2020 construction update

2nd floor hallway. Locker bases need to be poured. Once poured allows placement of ceramic tile
Main floor hallway- addition- ready for placement of ceramic tile. Thought: temporary heating may be needed.

Courtyard. Brick veneer near completion. Ready for landscape contractor / next week
Addition- brick veneer scheduled for completion/ end of this month
Childcare- SOG scheduled for Monday!