I am told doors /classrooms/ will be arriving 1st of next week!
Existing heat pumps to be removed from site!
Light fixtures stored in gym!
Bathroom door frames near completion
Heat pumps are placed in each classroom waiting for installation!
New light fixtures are being stored in each classroom!
Tile to be placed- washroom entrance!