New Gym- siding is now complete and masonry contractor is cleaning brick. We turn our thoughts completing exterior work. We are pushing for completion / of this project/ end of this month.
New Gym- painting of walls and ceiling / near completion. Up next – flooring.
New weight room. Ceiling- T bar has been framed and overhead lights placed. Locker base has been poured at entrance re- weight room.
Work on new classrooms main floor is ongoing. Masonry Contractor is / patching walls / make good.
We are coming to end of our journey and pushing for completion / end of this month.