Starting footings – new cafeteriaworking on footings- cafeteriaNew Columns Connecting to existing buildingPre-cast arrives Monday/ 3-4 days to place and groutWhen digging interior columns water enters quickly. We are hiring a Vac truck to clean out hole. Then immediately conctrete to be poured.2nd column