Bishop Reding- construction progress- Oct 29

Starting footings – new cafeteria
working on footings- cafeteria
New Columns
Connecting to existing building
Pre-cast arrives Monday/ 3-4 days to place and grout
When digging interior columns water enters quickly. We are hiring a Vac truck to clean out hole. Then immediately conctrete to be poured.
2nd column