Bishop Reding CSS- March 11/21- Const progress

Blog Summary: (AI Summaries by Summarizes)
  • The post discusses the importance of executive summaries for busy individuals.
  • It emphasizes the need for concise and clear communication in executive summaries.
  • Executive summaries should provide a brief overview of the main points and key findings.

New Gym- placement of brick veneer continues . Near completion.

Addition- sun deflectors over windows are now installed.

New Kitchens- school board has now moved in.

Theatre- Installation of bleachers near completion.

Dance rooms near completion- counter tops needed.

Former staff rooms- demolition has started.

2nd floor classroom and work room- placement of flooring / sheet goods/ near completion.

New Gym and weight Room – sheet metal contractor and electricians are working / above ceilings.

We are moving along well as I see progress on every visit. The light now is beaming at the end of the tunnel / Well Done.