Milton 10 CES- const update- Sept 15/21

Follow Us On Our Journey

Milton #10 CES- const progress- Sept 9/21

Masonry contractor building perimeter walls 2nd floor. Installation of metal duct, copper and sprinkler pipe / ongoing. Excavation of electrical duct bank has started.

Milton 10- Sept 7/21 – construction progress

Masonry contractor building perimeter walls 2nd floor. Next event is topping?

Nelson High School- Const progress/ Almost There

Below is a “cheezy” video I put together showing a walk-thru of the Kitchen Classroom, Cafeteria and Library. The end is near!! CLICK ON LINK BELOW- BEST VIEWED ON A