St. Mark CES- waiting for our roofer

Plywood parapet near completion! Curbs (RTU) are in place. / curbs for exhaust fans to be placed.Waiting for roof drains and M&E cones! Looking for GRRC ( our roofer) for Monday👍👍

Retaining Wall is ongoing and scheduled for completion – early next week. Mike (Wesley Paving) you’re on deck for sidewalk / mid next week!

Spraying of AVB starts next week followed with brick veneer!

Gas line has been installed – heating inside of building next week! Sprinkler contractor is onsite running his pipe😎😎

www.larryarbuckle.com

St. Mark CES- preparation (roof)

As discussed at yesterday’s site meeting, we are installing plywood (parapet) and placing curbs (cones) for roof top units! Once these tasks are complete will bring on our roofer- hopefully end of this week or Monday / at the latest! Pic below was taken yesterday! I will be returning Thurs (pm) to record progress and report. We need to be watertight ASAP!

Masonry block placed for lift ( stage)

www.larryarbuckle.com

St. Mark CES – Nov 12, 2018 update

The weather forecast appears  favourable for the next 2 weeks. We are installing plywood for our parapet [roof] and pushing for the start of our roofer [ end of the week]

We should start thinking of interior heat [ASAP]

 

 

We are starting our parapet wall [ plywood] and should be complete by tomorrow.

 

DCIM/103MEDIA/DJI_0419.JPG

We are well underway completing our retaining wall and have scheduled asphalt and sidewalk next week.

Once exterior walls dry out will bring on AVB spray- followed with brick veneer.

DCIM/103MEDIA/DJI_0417.JPG

2nd Request: we need curbs [RTU] and all cones placed prior to arrival of our Roofer {GRRC} George!!

DCIM/103MEDIA/DJI_0422.JPG

Placing masonry block [lift]

 

Metal Duct contractor is onsite. We are pushing T-bar ceilings starting the week of DEC 10th